Mid construction image of Wood Wharf building 3

Wood Wharf Building 3


Main Contractor: Canary Wharf Contractors Ltd
Engineer: Thornton Tomasetti
Architect: Allies and Morrison
Constructed: 2018/2019
Elland Value: £2.4 million
Project Tonnage: 750 tonnes


Elland Steel are providing steelwork for levels 11 to roof for this 15 storey building which is the next stage of the Wood Wharf development. The lower ten floors of the building are constructed using a concrete frame from which the steelwork provided by Elland is to be supported.

3D design image of Kings Cross

Kings Cross S1


Main Contractor: BAM Construction Ltd
Engineer: Ramboll
Architect: Weedon Architects
Constructed: 2019
Elland Value: £7.6 million
Project Tonnage: 2300 tonnes


A 195,000ft2, 12 storey building located at the corner of Handyside Street and Canal Reach in the Kings Cross area of London. It features 11 floors of Grade A office space, with the ground floor being retail space. The building features several expansive balconies and a roof-top landscaped garden. As much of the steel frame is to remain visible once complete careful considerations had to be made in the connection designs to ensure that they are aesthetically appealing.

Mid cionstruction image of Esplanade

Esplanade, Jersey


Main Contractor: Dandara
Engineer: Walsh Goodfellow
Architect: Axis Mason
Constructed: 2018
Elland Value: £3.35 million
Project Tonnage: 1200 tonnes


Located on the Esplanade in St Helier this 59,000ft2 storey office building is a beam and column to basement construction. Elland Steel are providing the structural steelwork, metal deck floor and pre-cast concrete stairs.

Aerial view of construction just prior to completion

Building 100, The Embankment Manchester


Main Contractor: BAM Construction Ltd
Engineer: Ramboll UK
Architect: Flanagan Lawerence
Constructed: 2018/2019
Elland Value: £4.95 million
Project Tonnage: 1773 Tonnes of Hot Rolled, 5 Tonnes of Cold Rolled


A 9 storey, 166,000ft2 Grade A office building with roof terrace located in the Greengate area of Salford, alongside its sister building, 101 Embankment. The building is constructed off a steel framed transfer slab above a car park which remained open during construction. The building has a metal deck floor and uses long span cellular floor beams to reduce the number of columns required, increasing the useable office space.

The New Members Club Under Construction

Wood Wharf Plot D1/D2, London


Main Contractor: Canary Wharf Contractors
Engineer: Thornton Tomasetti
Architect: Allies and Morrison
Constructed: 2019
Elland Value: £5.3 Million
Project Tonnage: 2250 tonnes


Elland Steel provided the structual steelwork and metal decking for this new 14 storey building forming part of the first phase of commercial buildings on the Wood Wharf development in London.

The New Members Club Under Construction

Quay Club, Heron Quay, London


Main Contractor: Canary Wharf Contractors
Engineer: ARUP
Architect: Adamson Associates Architects
Constructed: 2018
Elland Value: £4.2 million
Project Tonnage: 1600 tonnes


A new five-storey steel framed structure to accommodate exclusive guest rooms restaurants and leisure space. Elland Steel fabricated, supplied and installed 400t of weathering steel for the lower deck level which is sat on a series of existing piles over a portion of Middle Dock in Londonís Canary Wharf, as well as an additional 1,200t of steelwork for the main structure.

This unique contract posed a number of challenges, such as the need to use a temporary bracing strategy to limit the amount of loading applied to the piles, and the use of floating pontoons to enable access for workers and machinery during erection.

The Steel Frame Under Construction

King's Cross Bridge, London


Main Contractor: J Murphy & Sons Ltd.
Engineer: Ramboll
Architect: Latitude Architects
Constructed: 2018
Elland Value: £0.7 million
Project Tonnage: 230 tonnes


Elland Steel provided the metal decking and stairs along with fabricating, supplying and erecting the steel frame for this 18,000 sq ft office and retail building. Built on a basement slab which is the tunnel soffit of both the Metropolitan London Underground Line and the Moorgate National Rail Line close to Kingís Cross Station.

The confined nature of this central London site along with its location over active rail lines required careful planning to ensure that steelwork was delivered to site and erected on anti-vibration bearings whilst keeping disruption to a minimum.

Steelwork Being Erected In Sight Of The London Aquatics Centre

The International Quarter, London


Main Contractor: Lend Lease Ltd
Engineer: ARUP
Architect: Rogers Stirk Harbour & Partners
Constructed: 2016/17
Elland Value: £3.75 million
Project Tonnage: 1000 tonnes


This 650,000 ft2 grade A office has been prelet to the FCA (Financial Conduct Authority). This is the 2nd office of the 12 to be constructed over a 10 year period adjacent to the 2012 Olympic Park.