Ice Centre
Sheffield
The challenge to design a steel frame
within the clients cost plan and Architectural scheme
requirements began in earnest some ten months prior to steel
erection commencing on site.
Elland steel structures Ltd together with
the design team and HBG Construction worked closely and
expediently with the ultimate aim of providing the most cost
effective value engineered steel frame whilst not detracting
from the architectural features and scheme concepts.
Specific areas were targeted and re-visited
by the whole team with the sole purpose of achieving our goals
such was the effort and attention to detail in the early stages
that once in production the variations were minimal.
The steel frame consisted of a four-storey
central spin core structure, adopting large diameter CHS columns
together with compositely designed floor beams in conjunction
with profiled composite floor decking. Adjacent to this central
core area are two 48m wide x 72m long rink structures. The
competition & recreational ice rinks are column free spaces,
achieved by the design of 48m clear span curved lattice roof
trusses at 7.200m centres along the length of the building.
Within the competition rink is a seated viewing area similar in
construction to the premier league football grounds around the
country, providing a “bowl effect” arena with unobstructed
viewing to all the ice rink personnel and the paying public.
With the fact that a large quantity of the steelwork on this
project is a height, the client wanted a maintenance regime kept
to a minimum, as such Elland Steel applied off-site a series of
high quality paint systems that in conjunction with site applied
decretive coat produced a treatment protection for the steelwork
of 20 years to 1st maintenance. This provides the
client with a solution that means the rinks will not require
closure for maintenance every five or so years, together with
the associated health and safety issues involved in carrying out
the maintenance at heights.
Elland Steel Structures Ltd designed,
supplied, manufactured and installed approximately 750 tonnes of
high quality structural steelwork together with approximately
3,500 m2 of profile composite flooring, all ahead of the
contractors programme and to cost budget.
The architects and checking engineers for
the client was Building Design Partnership of Sheffield.
Programming and methods of construction we
also developed at an early stage allowing the steelwork to be
erected on a fast-track basis in a safe manner giving the
opportunity for following sub trades to achieve best
performance.
Elland Steel Structures Ltd were chosen as preferred supplier
working within the realms of Supply Chain Management, the
project highlighted the mutual benefits widely recognised in the
construction industry as a key competent skill.
|